MSP Metallics Ltd to set up Integrated Steel Plant at Marakuta, Jharsuguda

 

MSP Metallics Ltd to set up Integrated Steel Plant at Marakuta, Jharsuguda district in Orissa. The project involves setting up of Integrated Steel Plant (Sponge Iron (10,50,000 TPA); Pig Iron (10,60,000 TPA), Pellet Plant (6,00,000 TPA); Steel Melting Shop (10,50,000 TPA); Captive Power Plant (85 MW), Coal Washery (15,00,000 TPA) and Coke Oven Battery (6,00,000 TPA) as per further details given below:

 

S.

N.

Unit/

Manufactur-ing

facilities

Technology /

Process

Annual capacity Phase-wise

 (MTPA)

Ultimate Annual Capacity (MTPA)

 

 

 

Phase-I

Phase-II

Phase-III

 

1

Sponge iron

Coal base Rotary kiln

1,20,000

2,64,000

6,64,000

10,50,000

2

Pig Iron

Mini Blast Furnace

1,88,000

1,05,000

7,67,000

10,60,000

3

Captive Power Plant

WHRB / CFBC (MW)

--

--

10 MW

--

--

75

 

85

4

Steel Melting shop (Mild Steel)

Induction Furnace (Ph. I)

Induction Furnace (Ph. II)

Arc Furnace with LD Converter (Ph-III)

48,000

--

--

2,15,400

--

 

 

 

7,86,600

 

 

 

10,50,000

5

Coal washery

Heavy dense media cyclone

 

--

 

7,00,000

 

8,00,000

 

15,00,000

6

Sinter Plant

Linear Sinter Machine

--

4,60,000

--

4,60,000

7

Pellet Plant

Grate Kiln Technology

--

6,00,000

--

6,00,000

8

Coke oven battery

Non-recovery type

Eco-friendly coke oven

 

--

 

--

 

6,00,000

 

6,00,000

Custom Search

Copyright © 2013 Ibis Research Information Services Pvt Ltd. All Rights Reserved.
Contact : Ibis Research Information Services Pvt Ltd., 28, Rajaji Street, NGO Colony
Guduvancherry, Chennai -603 202   Mobile : 0-97898-37940 email : ibischennai@gmail.com Privacy Policy