VMS Ispat to set up integrated steel plant at Belur in Dharwad district of Karnataka.  The project involves setting up of Integrated Steel Plant alongwith Captive Power Plant (22 MW, FBC & 8 MW, WHRB). The project will come up in area of 60 acres.  The total project cost is estimated at Rs. 1880 million. The new unit will manufacture the following products

Unit

Capacity

Sponge Iron Plant

4x100 TPD

Electric Arc Furnace

30 Ton

Ladle refining furnace

 35 Ton

Vacuum Degassing unit & continuous casting machine

1Nos.

Power Plant (WHRB & FBC)

30 MW

 Following will be manufactured: 

S.N.

Product

Capacity

1

Sponge Iron

400 TPD

2

Billets

500 TPD

3

Captive Power

                             FBC

                             WHRB

30 MW

22 MW

8 MW


Custom Search

Copyright © 2013 Ibis Research Information Services Pvt Ltd. All Rights Reserved.
Contact : Ibis Research Information Services Pvt Ltd., 28, Rajaji Street, NGO Colony
Guduvancherry, Chennai -603 202   Mobile : 0-97898-37940 email : ibischennai@gmail.com Privacy Policy