Gulab Steel & Power to set up integrated steel plant at Aregudem in Moktur mandal in Nalagonda district of Andhra Pradesh. Land requirement for the project is around 90 acres. The total project cost is estimated at Rs. 1150 million. The project involves setting up of the following.

S.N.

Plants

Capacity

1

Sponge Iron

60,000 TPA

2

M.S. Ingots

60,000 TPA

3

CTD Bars Rolling Mill

60,000 TPA

4

Pig Iron

48,000 TPA

5

Captive Power Plant

10 MW